Barrier Installation, Line Striping Planned at Night Next Week on Interstate 95 North in South Philadelphia
PennDOT announced barrier installation and line striping will occur at night next week on northbound I-95 in South Philadelphia under a $37.4 million project to perform high-priority repairs on interstate bridges, to maintain the functionality, safety, and mobility of the structures along critical corridors.
Motorists are advised of the following travel restriction:
- Wednesday, September 17, and Thursday, September 18, from 9 p.m. to 5 a.m. the following morning, a single lane closure will be in place on northbound I-95 between Packer Avenue and Christian Street.
Motorists are advised to allow extra time when traveling through the work area because backups and delays will occur. All scheduled activities are weather dependent.
Under this contract, PennDOT’s contractor will make repairs to the deteriorated bridge decks, superstructure components, and portions of the substructures as needed.
Work on the superstructures will include repairing fabricated structural steel, weld cracks, prestressed concrete beams, reinforced concrete bridge deck, bridge railing, guiderail, and steel sign supports; and replacing existing expansion joints, seal existing deck joints, and existing strip seal glands on the bridge decks.
Work on the substructures will include repairing or reconstructing bearing pedestals, steel fixed bearings, and deteriorated portions of concrete substructure; cleaning bridge seats; resetting expansion bearings; and removing debris from under the bridges.
In addition to bridge repairs, 11 overhead steel sign structures will be cleaned and repainted. Existing roadway lighting will also be upgraded to LED luminaires.
IEW Construction Group, Inc. of Hamilton, N.J., is the general contractor on the project, which is financed with 100 percent federal funds.